Popular Posts

Monday, 10 September 2018

McDermott completes pipeline installation for GWF 2 project




McDermott International Inc (MDR) has successfully completed the contract for phase two of the Greater Western Flank (GWF) project. The contract was awarded by Woodside Energy Ltd in January 2016.
McDermott was responsible for the procurement, fabrication, installation and testing of a series of pipeline buckle initiators, pipeline end terminations and foundation mudmats, in-line tee structures and approximately 21 miles (35 kilometers) of a 16-inch (40 centimeters) corrosion resistant alloy (CRA) pipeline extending from the existing Goodwyn A Platform to the Lady Nora and Pemberton field manifold locations.
McDermott deployed two of its speciality vessels to complete the installation phase, namely DLV 2000 for the pipelay campaign and the Lay Vessel 108 for the pre-lay and post-lay campaign. McDermott also set up an onshore portable and temporary double jointing facility at its Batam fabrication yard in Indonesia to simulate the offshore installation campaign.

No comments:

Post a Comment